Proposed project schedule:

 

 

  • Stage 1: close Bridge Avenue from Marshall St. to Minnie Maddern St.
  • Remove Pavement, Curb & Gutter, and sidewalk.
  • Install new storm sewer, sanitary sewer, and watermain.
  • Construct new traffic signals at Marshall, and Pedestrian Flasher at Hawthorne
  • Excavate and grade roadway, followed by installation of concrete curb, driveways, and sidewalk.
  • Pave Bridge Avenue to bituminous and re-open to traffic November 2020.

 

 

  • Resume Construction in the Spring 2021.
  • Close Bridge Avenue from Minnie Maddern St. to Hammer Road.
  • Remove pavement, curb & gutter, and sidewalk.
  • Install new storm sewer, sanitary sewer, and watermain.
  • Construct new traffic signals at Richway Drive & Hammer Road.
  • Excavate and grade roadway, followed by installation of concrete curb, driveways, and sidewalk.
  • Pave multi-use trail east of Bridge from Minnie Maddern to Hammer Road.
  • Pave Bridge Avenue and re-open to traffic.