Proposed project schedule:

- Stage 1: close Bridge Avenue from Marshall St. to Minnie Maddern St.
- Remove Pavement, Curb & Gutter, and sidewalk.
- Install new storm sewer, sanitary sewer, and watermain.
- Construct new traffic signals at Marshall, and Pedestrian Flasher at Hawthorne
- Excavate and grade roadway, followed by installation of concrete curb, driveways, and sidewalk.
- Pave Bridge Avenue to bituminous and re-open to traffic November 2020.
- Resume Construction in the Spring 2021.
- Close Bridge Avenue from Minnie Maddern St. to Hammer Road.
- Remove pavement, curb & gutter, and sidewalk.
- Install new storm sewer, sanitary sewer, and watermain.
- Construct new traffic signals at Richway Drive & Hammer Road.
- Excavate and grade roadway, followed by installation of concrete curb, driveways, and sidewalk.
- Pave multi-use trail east of Bridge from Minnie Maddern to Hammer Road.
- Pave Bridge Avenue and re-open to traffic.